December 18, 2024
Read time visible on live site

Product Updates: Planned Percentage Complete, Ability to add activities on Table/Gantt and Variance Reason Codes

Our December 2024 update introduces tracking project progress with Planned Percentage Complete (PPC), adding activities to your project from the Gantt view, and categorizing delays and schedule changes with variance codes.

Planned Percentage Complete (PPC): As construction projects evolve, staying on top of progress is crucial to ensuring timelines and budgets are met. That's why we're excited to introduce the Planned Percentage Complete feature. This feature lets you monitor your project's progress by comparing planned activities with actual completions. You can easily track how much of the project has been completed versus what was originally planned, offering a clear, data-driven overview of project health.


With this feature, you gain valuable insights into your project's status at a glance. It helps you identify gaps or delays early, enabling you to make informed decisions and adjust your plans to keep the project on track. The ability to switch between Planning and Committed states enhances flexibility. In the Planning state, you can freely adjust the schedule without worrying about locking progress updates, allowing you to fine-tune details. Once you're ready to track progress, switching to the Committed state locks your dates, ensuring updates are accurate and reflect actual progress. This gives you a reliable view of your project's advancement, reduces the risk of errors, and helps maintain alignment with your project goals and deadlines. Learn More

Ability to add activities on Gantt: You can now add activities directly from Gantt views, simplifying your project planning process. This feature allows you to quickly build, update, and manage your schedule in the view that best suits your workflow, saving time and reducing the need to switch between views. Whether you prefer the free flowing layout of the Canvas or the visual timeline of the Gantt chart, you can now easily add tasks in the most efficient way for your project. Learn More

Variance Reason Codes: Variance Reason Codes enable you to track and categorize delays or schedule changes in your project by applying variance reason to activities and tasks. Whether the delay is due to weather, resource issues, or any other reason, you can easily assign a variance code to each affected activity.

This feature gives you the ability to gain deeper insights into the reasons behind schedule variances. By categorizing delays, you can quickly identify patterns, uncover potential risks, and understand which factors are impacting your project timeline. Not only does this improve transparency across teams, but it also enhances reporting accuracy, making it easier to communicate project status with stakeholders. Learn More

Media Contacts

Let us show you what modern project scheduling looks like

sales@planera.io
75 E Santa Clara Street, San Jose CA 95113

Book a Demo

Let us show you in 30 mins how we can make you love your project scheduling with Planera

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Product Updates: Planned Percentage Complete, Ability to add activities on Table/Gantt and Variance Reason Codes
Planera Achieves SOC 2 Type 2 Compliance
Beyond Deadlines Podcast with Nitin Bhandari
Hugh Seaton Hosts Nitin Bhandari On His Constructed Futures Podcast
Planera raises $13.5M to help solve the gnarly problem of scheduling for construction contractors
5 Contech Firms Raise Over $126M
Sept '24 Updates: Multiple Float Path, Commenting in Table and Gantt and Projected S Curve
California State University, East Bay Study Finds Visual Construction Scheduling Superior to Tabular Scheduling
Navigating 2024: Construction Planning Trends That Will Define the Next Year
Save Filters to Use Later
Multiple Project Versions to Eliminate Clutter and Mistakes
Master Risk with Monte Carlo Simulations
Turbocharge Your Construction Scheduling: DCMA 14 integrated with CPM scheduling, a Game Changer!
Scotland Foss Joins Planera as Company’s First Head of Sales
Planera Integrates with Autodesk Construction Cloud for Streamlined Project Scheduling and Planning
Slice of Construction Podcast: Revolutionizing Scheduling with Nitin Bhandari, Co-Founder & CEO of Planera
Planera Secures $13.5 Million to Disrupt Construction Scheduling & Planning Market
New Features: More Colors, Insert/Dissolve and More
Planera Raises $5.4 Million in Seed Funding to Transform Construction Industry Project Planning
Planera Raises $13.5M in Funding, Plans to Double Down on Scheduling
Product Updates: New Trace Path, As Late as Possible Constraint, and Sorting options